Project Leadership and Delivery — Free Starter Lesson
Free Professional starter lesson · 15 minutes · Beginner
Plan a delivery and respond to a delay
Imagine your team is launching an online booking form for a community centre on Friday. You’ll make a short delivery plan, then update it when a dependency slips.
1. Define what counts as delivered
Write one sentence that names the user, the outcome, and the deadline. For example: By Friday at 15:00, a visitor can select a slot, submit the form, and receive confirmation. Use three successful test bookings and one rejected duplicate booking as your acceptance checks.
2. Work backwards from the deadline
Give each milestone one owner and one prerequisite. The form owner builds the form by Tuesday. The tester runs the acceptance checks by Thursday after the form is ready. The centre manager reviews the results and decides whether to launch on Friday.
3. Set an escalation trigger
Agree that the form owner will flag any forecast delay beyond Wednesday noon. The project lead then tells the centre manager which checks are at risk and when a launch decision is needed.
Try it yourself
The form is now expected on Thursday afternoon, and the tester is available only Thursday morning. Write a three-line update giving the impact, your recommendation, and who decides by when. Keep the acceptance checks in your revised plan.
Self-check: Your message should say that the planned test window is lost, name the next available test slot or another tester, and ask the centre manager to confirm a realistic launch date before visitors are told it is live.
Watch the Project Leadership video.